On any selinux-policy PR, Zuul always fails immediately with a comment such as:

Unable to freeze job graph: Unable to modify final job attribute timeout=21600 with variant

See for example:
https://src.fedoraproject.org/rpms/selinux-policy/pull-request/320

This has been happening for a long time now, just AFAIK was never reported here.


Metadata Update from @fbo:
- Issue tagged with: Zuul CI

Hi,

Thanks for the report. This should be fixed now with the land of https://pagure.io/fedora-zuul-jobs-config/pull-request/171.

I did a recheck and jobs started.

I close the issue. Please re-open if needed.

Metadata Update from @fbo:
- Issue status updated to: Closed (was: Open)