New PDU (Power Distribution Units) are being put into various racks in IAD2. We need to have short outages when the servers are being moved to new power AND we will need to get the configurations for each of the PDU's so we can do remote power cycles of systems.
Metadata Update from @smooge: - Issue priority set to: Waiting on Assignee (was: Needs Review) - Issue tagged with: hardware, medium-gain, medium-trouble, ops
I asked about this, but didn't get a answer really on chat. I'll try sending an email.
I'll ask again. No current status known.
Will check again, still no known status.
Metadata Update from @kevin: - Issue tagged with: blocked
I got an update yesterday. The racks should be configured in PowerIQ. Red Hat employees in CPE will need to get logins and set up the ports accordingly.
Metadata Update from @zlopez: - Issue untagged with: blocked
We now have access to poweriq and can power cycle things.
That said, there's an issue with one of the pdu's showing nothing on on it and some of the devices don't list what ports they are connected to.
However, this ticket is done and we just need to work with RHIT to get things 100% working.
Metadata Update from @kevin: - Issue close_status updated to: Fixed - Issue status updated to: Closed (was: Open)
Log in to comment on this ticket.