Optimal time to do the event Shouldn't be against major event (festivals, conferences, etc) TZ!!
Metadata Update from @siddharthvipul1: - Issue tagged with: planning
Jona and I think March and April are good months for this but we need to avoid following events (and possibly more)
It'd probably be good to avoid the Beta and Final freezes on the Fedora Linux release schedules, too, as those will be busy times for mentors involved in QA, development, and release engineering activities. That basically takes out March and April, though, as well as September and October.
Preferred days:
@riecatnor hey, so would you have any input on which days work better for community members? (assumption derived from attendance on other events say Friday-Saturday vs Saturday-Sunday)
That basically takes out March and April, though, as well as September and October.
What do you think about early March or late April?
Metadata Update from @siddharthvipul1: - Issue marked as blocking: #1
As @bcotton suggested, we should avoid Beta & Final freezes here are the dates for those:
Tue 2022-02-22
Tue 2022-03-15
Tue 2022-04-05
Tue 2022-04-19
@jonatoni and I had a call yesterday and April 1st and 2nd (or 2nd and 3rd) suits our timeline -- which also avoids Freeze! Do we think that could be a possibility?
That would work, so long as we don't slip beta too far again. Seems like a reasonable risk to take, though.
Hi @siddharthvipul1 - thanks for working on this!
For the Release Parties I notice we have the most attendance on Friday AM (EST). I would def suggest choosing Friday & Saturday over Saturday & Sunday. April 1st and 2nd seem good.
yes, it gives us 2 weeks of wiggle room. If beta slips for 2 weeks, we still won't be in the freeze timeline (if we go with April 1st and 2nd). so reasonable enough \o/
Hi @siddharthvipul1 - thanks for working on this! For the Release Parties I notice we have the most attendance on Friday AM (EST). I would def suggest choosing Friday & Saturday over Saturday & Sunday. April 1st and 2nd seem good.
Perfect I will wait for 2 days and if I don't see any major -ve to the date, I say we proceed with this. Next step would be the request hopin access for those day -- which I will do in a couple of days (🤞)
Date confirmed: April 1st and 2nd Thank you everyone for participating in the discussion. We can decide the time later -- based on the content We are targeting 7-8 hours (4/3 each day) Closing this ticket as fixed
Metadata Update from @siddharthvipul1: - Issue status updated to: Closed (was: Open)